I-595 Bridges Fender System Replacement Project over the South Fork of the New River in Fort Lauderdale

Financial Number: 429095-1-52-01

Project Length: 0.131 miles

Project Limits: Underneath the I-595 bridges over the south fork of the New River

Start Date: June 16, 2014

Completion Date: November 12, 2014

Contractor: Sieg and Sons, Inc

Estimated Construction Cost: $582,300

Scope of Work: Project improvements included replacing marine fenders and navigation lights underneath the I-595 bridges over the south fork of the New River.


Click here for upcoming lane closures

 

Project Photos

Pre-Construction

Click to view enlarged version/details
Pre-construction Photo

During Construction

Click to view enlarged version/details
Pre-construction Photo Pre-construction Photo Pre-construction Photo Pre-construction Photo
 

Florida Department of Transportation
Florida Department of Transportation
Florida 511 Travel Info
FDOT District Four Youtube
SunGuide
Kids Zone
75 Express
95 Express
zero