Financial Number:
429095-1-52-01
Project Length: 0.131 miles
Project Limits: Underneath the I-595 bridges over the south fork of the New River
Start Date: June 16, 2014
Completion Date: November 12, 2014
Contractor: Sieg and Sons, Inc
Estimated Construction Cost: $582,300
Scope of Work: Project improvements included replacing marine fenders and navigation lights underneath the I-595 bridges over the south fork of the New River.
Click here for upcoming lane closures |